Abstract

Technological progress in tunneling has led to modern and efficient tunneling methods in vast underground spaces even under inappropriate geological conditions. Identification and access to appropriate and sufficient geological hazard data are key elements to successful construction of underground structures. Choice of the method, excavation machine, and prediction of suitable solutions to overcome undesirable conditions depend on geological studies and hazard analysis. Identifying and investigating the ground hazards in excavating urban tunnels by an EPB machine could augment the strategy for improving soil conditions during excavation operations. In this paper, challenges such as geological hazards, abrasion of the machine cutting tools, clogging around these tools and inside the chamber, diverse work front, severe water level fluctuations, existence of water, and fine-grained particles in the route were recognized in a study of Tehran subway line 7, for which solutions such as low speed boring, regular cutter head checks, application of soil improving agents, and appropriate grouting were presented and discussed. Due to the presence of fine particles in the route, foam employment was suggested as the optimum strategy where no filler is needed.

Keywords


[1]. Iranian Tunnelling Association (http://www.irta.ir)
[2]. International Tunnelling And Underground Space Association (http://www.ita-aites.org)
[3]. USA - UCA of SME - Underground Construction Association of SME (uca.smenet.org)
[4]. Guglielmetti , V., Grasso, P., Mahtab, , M., & Shulin, X. (2007). "Mechanized tunnellling in urban areas"., Turin, Italy: Taylor & Francis Group.
[5]. Langmaack, L. (2006). "EPB tunnelling – chances and limits. symposium on :Utilisation of underground space in urban areas"., Darmstadt, Germany: Sharm el-sheikh, Egypt.
[6]. Lambert, J.H., and Haimes, Y.Y., and Li, D., and Schooff, R.M., Tulsiani, V., (2001). "Identification, ranking, and management of risks in a major system acquisition", Reliability Engineering and system Safety, No. 72, pp. 315-325.
[7]. Ghosh, S and Jintanapakanont, J., (2004). ''Identifying and assessing the critical risk factors in an underground rail project in Thailand: a factor analysis approach"; International Journal of Project Management, Vol. 22, pp. 633–643.
[8]. Wagner, H., (2006). "Risk Evaluation and Control in Underground Construction"; International Symposium on Underground Excavation and Tunneling. 2-4 February, Bangkok: Thailand.
[9]. Herrenknecht, M. Bappler, K., (2006). "Mastering risks during mechanized excavation in urban centers with highly complex ground conditions".
[10]. Degn Eskesen, S., Tengborg, P., Kampmann, J., Holst Veicherts, T, (2004). "Guidelines for tunnelling risk management: International Tunnelling Association", Working Group No.2,
[11]. Beard, A. N., (2010). "Tunnel safety, risk assessment and decision-making", Tunnelling and Underground Space Technology, Vol. 25, pp. 91–94.
[12]. Isaksson, T., Stille, H., (2005). "Model for Estimation of Time and Cost for Tunnel Projects Based on Risk Evaluation", Rock Mechanic and Rock Engineering, Vol. 38, No. 5, pp. 373–398.
[13]. Pipattanapiwong, J., (2004). "Development of multiparty risk and uncertainty management process for an infrastructure project", Doctoral dissertation, Kochi University of Technology.
[14]. PMI (Project Management Institute); (2004). "a Guide to the Project Management Body of Knowledge (PMBOK Guide)"., Pennsylvania, Newtown Square.
[15]. BTS/ABI, (2003). "The Joint Code of Practice for Risk Management of Tunnel Works in the UK", London: BTS. (www.britishtunnelling.org).
[16]. Sepasad Engineering Company. (2008). "Execution Method, Machine Choice and TBM Technical Specifications of Tehran Subway Line 7". Tehran,Iran: Sepasad Engineering Company.
[17]. Sahel Consulting Engineers . (2008). "Engineering Geology Report of the Eastern-Western Part of Tehran Subway Line 7 Tunnel". Tehran: Sepasad Engineering Company.
[18]. Thuro, K., & Kasling, H. (2009). "Classification of the abrasiveness of soil and rock". Geomechanics and Tunnelling, No.2; 179-188.
[19]. Thuro, k., & Plinninger, R. (2003). "Hard rock tunnel boring, cutting, drilling and blasting: rock parameters for excavability". Tunneling roadmap for rock mechanics.
[20]. Sahel Consulting Engineers. (2011). "Engineering Report of the Eastern-Western Part of Tehran Subway Line 7" . Tehran, Iran: Sepasad Engineering Company.
[21]. Thewes, M., & Burger , W. (2004). "Clogging risks for TBM drives in clay". Tunnels & Tunneling International, 28-31.
[22]. Thewes, M., & Burger, W. (2005). "Clogging risks for TBM drives in clay – identification and mitigation of risks". Underground space use : Analysis of the past and lessons for the future (pp. Vol. 1-2). London: Taylor & Francis Group.
[23]. Finno, R., & Clough, G. (1985). "Evaluation of soil respone to EPB shield Tunnelling". Journal of Geotechnical Engineering, 111-155.
[24]. Feinendegen, M., Ziegler, M., Spagnoli, G., Fernandez – steeger, T., & Stanjek, H. (2010). "A new laboratory test to evaluate the problem of clogging in mechanical tunnel driving".,
[25]. Seli, T. M.–L.–W. (2008). "Description of the Supply of one Earth Pressure Balance TBM with Relevent Modular Back – up System"., Tehran, Iran: Sepasad Engineering Company.
[26]. Standing, J., Kjekstad, O., & Kastner, R. (2003). "Avoiding Damage Caused by Soil – Structure Interaction" : Lessons Learnt From Case Histories. London: Thomas Telford.
[27]. Engineers, J. S. (1996). "Japanese standard for shield tunnelling"., Japan: Committee of Tunnel Engineering.
[28]. Williamson, G., Traylor, M., & Higuchi, M. (1999). "Soil Conditioning for EPB Shield Tunneling on the South Bay Ocean Outfall"., In SME, Rapid Excavation and Tunneling Conference Proceedings (p. 29), SME.
[29]. Herrenknecht, M., & Frenzel, C. (2005). "Long Tunnels in Hard Rock – A Preliminary Review"., (pp. 343-349). Bauingenieur 80.